Project Description产品描述
LV capacitor banks with DE-TUNED filters for reactive power compensation
基于无调谐滤波器的低压无功补偿电容器组
The Repsol Industrial Complex in Tarragona is a set of facilities in which a large number of petroleum products are produced. Its importance has been increasing since its inception, as well as its production and storage capacity.
塔拉戈纳雷普索尔工业区含有一个生产大量石油产品的设施。它的重要性自成立以来一直在增加,正如同它的生产和储存能力。
Currently the complex occupies more than 500 hectares. Tarragona Repsol currently has four major areas: refining and chemistry (in the Industrial Complex) and LPG and exploration.
Currently the complex occupies more than 500 hectares. Tarragona Repsol currently has four major areas: refining and chemistry (in the Industrial Complex) and LPG and exploration.
目前该建筑占地500公顷以上。塔拉贡纳雷普索尔目前有四个主要领域:炼油和化学(在工业综合体)和液化石油气和勘探。
LIFASA was part of the compensation project in its facilities located in Tarragona, supplying several batteries of low voltage capacitors with filters to reduce and compensate the Reactive Energy present in their electrical installations. Therefore, improvements have been implemented in the system of its electrical network, thus improving voltage losses and increasing the power available in the secondary transformers.
LIFASA是塔拉戈纳的设施改造中补偿项目的供应商之一,它向几个低压电容器柜提供滤波器,以减少和补偿其电气设备中存在的无功能量。因此,对其电网系统进行了改进,从而改善了电压损耗,增加了二次变压器的可用功率。
LOCATION 项目位置
Tarragona, Spain 西班牙 塔拉贡纳
YEAR OF ACHIEVEMENT 完工时间
March 2012